Task planned hour is changed to Actual hour (Unexpected behaviour) RRS feed

  • Question

  • I am using "SINGLE ENTRY MODE" .

    and then assign one task to resource of one day.

    when resource see its task at its timesheet . there is 8 hours planned work task.

    and when resource enter 4 hour actual in this task.

    the planned is also changed to 4 hour and also the same in Resource usage view.

    Why this happened. and how we can see planned hour of task.

    tell me about this behaviour.

    Wednesday, August 22, 2012 5:30 AM

Answers

  • John Eddie --
     
    In Microsoft Project and Project Server, actual work always replaces planned work.  That is why you are seeing what you see, even if unexpected.  This is why your PMs need to save a Baseline in their projects before team members begin entering progress in PWA.  If the PM saves the Baseline, then he/she can compare the original planned work for the task in the Task Usage view, which would show the 8 hours per day.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by John.Eddie Wednesday, August 22, 2012 1:54 PM
    Wednesday, August 22, 2012 1:22 PM