none
Project Server 2010 Cannot edit previous week timesheet RRS feed

  • Question

  • I cannot edit a timesheet from a previous week. The task is set to start before that week. The timesheet can be edited for the current week and going forward. Any ideas?
    Wednesday, August 3, 2011 10:18 PM

Answers

All replies

  • Hi there,

    Have you closed that timesheet period? check in Server settings > Time Reporting Periods.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Wednesday, August 3, 2011 10:34 PM
    Moderator
  • Great question. No the time period is not closed.

    Does it have to do with the way the task is set up? Interesting how the task does not indicate the task name for the week unlike it does for the next week - but the user is assigned to the task before the week in question.

    Wednesday, August 3, 2011 11:09 PM
  • So to confirm, the user doesn't see this task on the previous week's timesheet? Is it just one particular task that this user cannot add time to or all tasks in that period? What does the status bar show for that timesheet when you open the timesheet from the previous week?

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Thursday, August 4, 2011 8:31 AM
    Moderator
  • The status in Manage Timesheet's is "Not Yet Created". There is only one task assigned to the resource so it should exist in the timesheet.
    Thursday, August 4, 2011 5:34 PM
  • Can the user click the "Click to create" drop down menu then click Create with tasks? What happens then?

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Thursday, August 4, 2011 6:19 PM
    Moderator
  • Yes and that's when the timesheet shows it does not have a task when it really does. Could this be a permissions issue? I'm using claims based auth.
    Thursday, August 4, 2011 8:35 PM
  • It wont be a permission issue if that resource is assigned to that task. I would ask the user to insert row > insert task, then select the task and click ok.

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    • Marked as answer by dovendaven Thursday, August 18, 2011 12:57 AM
    Thursday, August 4, 2011 9:00 PM
    Moderator
  • Yeah, it was glitchin some how. I''ve moved on as you mentioned.
    Thursday, August 18, 2011 12:58 AM