Timephased Work Different than Total Work RRS feed

  • Question

  • Hello,

    When looking at the resource usage view I am finding a few cases where the total in the work column does not match the total in the timephased view. Is there a way to sync the two? What could have caused this?

    Thanks,

    Jessica


    Jessica Hancock

    Wednesday, May 13, 2015 8:21 PM

All replies

  • Jessica --

    What version of Microsoft Project are you using?  Are you using the software with Project Server, or are you using the Microsoft Project desktop application only?

    If you have multiple projects open in Microsoft Project and then you apply the Resource Usage view, please keep in mind that this view shows EVERY resource in EVERY open project.  Would that explain any of the discrepancies you are seeing?

    Please let us know the answers to my questions and we will try to help you.


    Dale A. Howard [MVP]

    Wednesday, May 13, 2015 9:44 PM
    Moderator