  • dear friends
    my resources are 2 kind of workers (i.e plasterer & builder)
    but i have one task that both of them can do (i.e cleaning)
    and i want to choose one of them only according to the availability.
    i don't know how to set it up
    and i will appreciate your help
    thanks
    Gilad

    Thursday, June 26, 2014 4:06 PM

Answers

  • Hi Gilad,

    You can use the resource availability option in the build team page (in MSP or Web both places) where you will find the availability.

    Regards,

    Saurav Chakravorty | Sr. EPM Consultant