  • Question

  • I have an enterprise task custom cost field, configured to rollup as sum.  When I inactivate the task the entered cost in this field continues to contribute to the rollup, even though the task is inactive.  I want this custom cost field to act just like the normal cost field, and suppress the contribution to the rollup when the task becomes inactive.  Is this a bug?  Is there a setting I have missed?


    Wednesday, August 12, 2015 6:21 PM

All replies

  • Hi Steven,

    I cannot reproduce your issue with Project 2016 Preview. Which Project version and patch level are you using? Has the task been created from a template? Can you reproduce this unexpected behavior on a new blank project?


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Thursday, August 13, 2015 7:22 AM
    Moderator