none
Confirmed (Task field) in Project Pro RRS feed

  • Question

  • Hi,

    What is the use of the field Confirmed (Task field) ?

    When and where a resource can set it to Yes?

    Thanks

    Monday, March 6, 2017 2:11 PM

Answers

  • Robert6165,

    The Confirmed field is determined by resource action. Outside of Project Server (i.e. not using Project Server), go to the Resource Usage view. Add the Confirmed field. For each assignment row that the resource accepts the assignment, set the confirmed value to "Yes". This will reflect in a Task view (e.g. Gantt Chart view).

    Hope this helps.

    John

    • Marked as answer by Robert6156 Thursday, March 9, 2017 10:03 PM
    Monday, March 6, 2017 2:25 PM