Resource Overallocation Indication in Project Server 2013 RRS feed

  • Question

  • Hi,

    I have a project, in which resources are allocated to the tasks.

    I open two projects at a time and open Resource Usage view, I see red colour indication for the resources even they are not overallocated( I mean in Resource usage view in Timephase grid I can see 8hrs per day in Red color)

    May I know why is that?


    K.Gokulraj

    Thursday, June 25, 2015 10:01 AM

All replies

  • I would suggest going to Resource Center and select the resource/s that you are finding Overallocated, click "Resource Assignments" or "Resource Availability" you will get details of the assignment with actual hours by date  from  "Resource Availability"

    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, June 25, 2015 10:42 AM
  • Hi

    project will show red colour even if there are two tasks with 100% allocation that end on 9am that day and no other task.

    This will lead to a 200% allocation from 8 to9 and 2h work on that day. No "real" overallocation, but if both tasks need to be finished at 9am, you would have a problem.

    Kind regards

    Christoph


    Christoph Muelder | Senior Consultant, MCTS, MCSE | SOLVIN information management GmbH, Germany

    Friday, July 10, 2015 1:36 PM