Task Starts and Finishes in Feb Task Usage Shows Work Hours in Jan column RRS feed

  • Question

  • MSP 13 Pro

    Work week starts on Thursday - following issue occurs

    Task starts and finishes in February.  Task Usage view shows hours for the task in January.

    Work week starts on Sunday - no issue

    Task starts and finishes in February.  Task Usage view shows hours for the task in February.

    I saw a similar question and the answer to solve that issue was to start the project on the 1st day of the work week.  I changed our Project Start Date from Monday to Thursday and still have the issue based on the Work week starts setting.  The only "Work week starts" day of the week where the usage tables work correctly is Sunday!

    Wednesday, September 23, 2015 9:38 PM