  • Question

  • Is it possible to automatically group tasks per week (using some view or at least some report)?

    My client wants to know how each week is planned and if some kind of delay happens, I need to reorganize all weeks manually. Currently my tasks are organized like this:

    Project Name

    |_ Week 1

           |_ Task 1

           |_ Task 2

           |_ Task 3

    |_ Week 2

           |_ Task 4

           |_ Task 5

           |_ Task 6


    If you found this post helpful, please "Vote as Helpful". If it actually answered your question, remember to "Mark as Answer". Se achou este post útil, por favor clique em "Votar como útil". Se por um acaso respondeu sua dúvida, lembre de "Marcar como Resposta".

    Wednesday, November 4, 2015 2:17 PM

Answers

All replies