Will DPM 2012 support Long Term To Tape Incremental backups? RRS feed

  • Question

  • As far as I can tell, DPM 2010 only supports Short Term To Tape Incremental backups (and at that, only if you choose "Daily" instead of "Weekly" as the option).   When using Long Term to Tape, only Full Backups are performed.

    Does anyone know if DPM 2012 will support Incremental backups for Long Term to Tape?  This is sorely needed by us in our situation, and we would love to see this feature added. 

    Monday, April 30, 2012 3:10 PM

Answers

  • Hi,

    There is no change in DPM 2012, sorry.


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. Regards, Mike J. [MSFT] This posting is provided "AS IS" with no warranties, and confers no rights.

    Wednesday, May 2, 2012 2:55 AM