Can we define different timesheet periods - Project server 2007 RRS feed

  • Question

  • Hi,

    Say in our settings under timesheet periods we have week defined starting Monday to Sunday. Ideally all 2013 periods until now have this pattern (15weeks)

    Now we want to change the pattern of the week to start from Sunday to Saturday after 15th Apr. So ideally

    2013 week 16 will start on Monday 15 Apr, will have only 6 days and end on Saturday 20-04

    2013 week 17 will have 7 days, from Sunday 21-04 > Saturday 27-04.

    All future timesheet will start on Sunday and have 7 days.

    The existing timesheet that were created for the whole year need to be deleted as we are changing the pattern after 15th apr

     My question is can we do this and have about 3 differnt types of periods within an instance. If any workaround please suggest

    Thanks

    mp

    Thursday, April 11, 2013 2:08 PM

Answers

  • You can do that, as long as no one has already submitted a timesheet for any of the periods you want to change.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    • Marked as answer by Mac_cs Thursday, April 11, 2013 5:51 PM
    Thursday, April 11, 2013 3:20 PM

All replies

  • You can do that, as long as no one has already submitted a timesheet for any of the periods you want to change.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    • Marked as answer by Mac_cs Thursday, April 11, 2013 5:51 PM
    Thursday, April 11, 2013 3:20 PM
  • Thanks Reid, i understand this;

    Thursday, April 11, 2013 5:51 PM