Resource Availability not accurate RRS feed

  • Question

  • I'm using Project Online - Resource Center. When checking resource availability, I choose the Assignment Work By Resource view. The project schedule has committed resources chosen from enterprise resource pool and it has been published a few times already. The Resource availability graph has nothing displaying for the resource even though I have confirmed work has been assigned for the task for the resource. It's a blank graph and I know there has been work assigned. Anyone else seen this or have an idea?
    Tuesday, January 17, 2017 8:11 PM

All replies

  • Hi,

    Are you looking at the right time period? Which view are you using? I know that there was a bug on the resource utilization per projects view, displaying no data, but it should be fixed by now.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, January 18, 2017 7:52 AM
    Moderator
  • I needed to publish schedule from web, then change the resource plan option to calculate from project schedule, then resource center was finally accurate. trick is to publish schedule from the web not the client.
    Tuesday, April 4, 2017 7:28 PM