Machine work hour connect with diesel as material RRS feed

  • Question

  • Dear Sir,

    Kindly let me know, How to connect machine work hour to diesel as material, that shows in resources uses window? As machine works for 6hr so diesel cost distributed in this 6hr for machine take 5 lt/hr?

    Thanks

    jssvish


    • Edited by Jssvish Thursday, December 14, 2017 9:01 AM
    Thursday, December 14, 2017 7:10 AM

Answers

  • Hi Jssvish,

    There is nothing you can do.  You will need to manually calculate how much diesel to use based upon the number of hours the machine is working....


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    • Marked as answer by Jssvish Friday, December 15, 2017 12:45 PM
    Friday, December 15, 2017 8:41 AM
    Moderator

All replies

  • Hi Jssvish,

    The concept of connecting peices of equipment and resources together is not something that exists in MS Project.  


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Thursday, December 14, 2017 7:39 AM
    Moderator
  • Sir,

    Kindly suggest me there is any possibilities , how to connect machine hour with diesel cost each other?


    Thanks & regards

    Jssvish

    Friday, December 15, 2017 5:16 AM
  • Hi Jssvish,

    There is nothing you can do.  You will need to manually calculate how much diesel to use based upon the number of hours the machine is working....


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    • Marked as answer by Jssvish Friday, December 15, 2017 12:45 PM