While assinging an enterprise resource to a task, project professional is automatically splitting the resource into first name and last name as two different resources in Project Professional 2010 RRS feed

  • Question


  • Hi,

     

    One of our Project Professional 2010 user is facing a strage issue. While She is assigning an enterprise resource to a task, automatically the first name and last name are splitting into two different resources under the same task. Where as if she try to assign the resource by selecting the task and goto Resource tab --> Assign Resource, it is not happening, however, when she double click on the task and go to the Resource tab in the window which pops up and add the resource to the List. As soon as click OK, all the Resources (even the ones added before) split into two: Familiy name and first name in separate lines and the whole Resource List gets immediately complemented by local resources equal to all of these name fractions.

    Please suggest how to over come this issue.

    Thanks,

    Kiran.