how to replace inactive resource who has actual s in project with a new one in MS project 2010 RRS feed

  • Question

  • how to replace inactive resource who has actual s in project with a new one in MS project 2010?
    Monday, August 11, 2014 4:28 PM

All replies

  • Hi,

    From the resource tab, click "add resources" then open the enterprise resource pool.

    On the left side (enterprise resources), select the new resources and on the right side (project resources) select the resource to be replaced. Finally click on the "replace" button. 

    Note that the inactive resource will be kept in the project team and the assignments with actual will stay as is. Only the remaining work will be assigned to the new resource.


    Hope this helps,