  • Hello everyone,

    Project server security is not restricting the projects in portfolio project selection window, how I can configure it to show only their projects which are visible to the user (not from the view)?

    *Here security is configured with RBS.

    Note: I am using Project server 2010.

    Regards,


    Avinash kumar | e2eProjects Pvt. Ltd | Blog:http://om-avinash.blogspot.com

    Sunday, November 4, 2012 10:52 AM

Answers

  • Hi Avinash

    it's intended to works that way and is default behaviour, as the selected projects are based on views & by default there is only 1 summary view available for both Portfolio Analysis & Portfolio Analysis project selection, you might want to put a filter for filtering out projects based on your requirement 

    Reason for making those projects still available lies in the basic question of portfolio analysis, wherein you analyze both new & existing projects(in execution) as well for reasons to optimize your ongoing portfolio which include currently executing projects as well, wherein there might be a need to  kill a project or refund an existing project to make it early or to re resource it hence it includes all projects & by default a porfolio analyzer should be able to see all projects to optimize

    Let me know, if this answers your question


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    Friday, November 9, 2012 4:07 PM
    Moderator

All replies

  • What roles have you given the user? 

    If you want to restrict the number of projects, then you will need a custom group, similar to the Portfolio Manager, except you will need to enable the RBS security.

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA, MCC 2011, MCC2012
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Monday, November 5, 2012 4:27 AM
    Moderator
  • Hi Avinash

    it's intended to works that way and is default behaviour, as the selected projects are based on views & by default there is only 1 summary view available for both Portfolio Analysis & Portfolio Analysis project selection, you might want to put a filter for filtering out projects based on your requirement 

    Reason for making those projects still available lies in the basic question of portfolio analysis, wherein you analyze both new & existing projects(in execution) as well for reasons to optimize your ongoing portfolio which include currently executing projects as well, wherein there might be a need to  kill a project or refund an existing project to make it early or to re resource it hence it includes all projects & by default a porfolio analyzer should be able to see all projects to optimize

    Let me know, if this answers your question


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    Friday, November 9, 2012 4:07 PM
    Moderator
  • Thank you Sunil Kumar Singh and Michael Wharton for your reply, so finaly I have only one way to restrict the project through view's filter.

    Thanks and Regards,