Backup Timing start and end RRS feed

  • Question

  • Dear,

    How I can find out the backup timings: Start Timing and ending timings

    Please assist me.

    Regards,

    MD


    MD
    Monday, August 8, 2011 8:59 AM

Answers

  • Hi,

     

    You can look in the DPM Management console under Monitoring/Jobs and get the start time and time elapsed for completed jobs and failed jobs.

     

    Thanks,

    Marc

    Tuesday, August 9, 2011 1:14 PM
    Moderator

All replies

  • Dear,

    How I can find out the backup timings in DPM 2010: Start Timing and Finish Timings

    Please assist me.

    Regards,

    MD


    MD
    Monday, August 8, 2011 9:01 AM
  • Hi,

     

    You can look in the DPM Management console under Monitoring/Jobs and get the start time and time elapsed for completed jobs and failed jobs.

     

    Thanks,

    Marc

    Tuesday, August 9, 2011 1:14 PM
    Moderator