Block resource from enagement to Project Task RRS feed

  • Question

  • Hi..

    I am using Project Pro 2016 (Version No 15.0.4128.1014)..

    I have enabled engagement feature... now I have added a new engagement for user (AAA) with 30% unit for one month.. then I have got approval from status manager..

    Is this possible to affect the resource availability for this project  to 30% in User AAA.

    once i got approval from status manager, the % of unit will be effort on project resource..

    if i add a task to AAAA it must take the 30% Planned hours..

    Is this possible or i am wrong ..

    Please help me to resolve this..

    Thanks

    Monday, April 24, 2017 5:42 AM

Answers

  • Hi,

    sorry, this is not possible. With a user requiring an engagement, you will only see an indicator if assignments are exceeding existing engagements. Existing engagements will not prevent you from creating assignments with any value.

    Regards
    Barbara

    • Marked as answer by TalhaTJ Monday, April 24, 2017 12:55 PM
    Monday, April 24, 2017 5:53 AM