Task Sequencing RRS feed

  • Question

  • MS project assigns a Task ID to each tasks, but when I group the tasks I want to have a way to temporarily re-sequence the tasks after a new grouping.
    Wednesday, December 9, 2015 12:39 PM

Answers

  • Ed  --

    When grouping is not applied, you can renumber the task ID field using the Sort By dialog (click View > Sort > Sort by).  When grouping IS applied, you can sort the tasks but you cannot renumber the task ID field.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, December 9, 2015 6:09 PM
    Moderator

All replies

  • Ed  --

    When grouping is not applied, you can renumber the task ID field using the Sort By dialog (click View > Sort > Sort by).  When grouping IS applied, you can sort the tasks but you cannot renumber the task ID field.  Hope this helps.


    Dale A. Howard [MVP]

    Wednesday, December 9, 2015 6:09 PM
    Moderator
  • Excellent. Just what I was looking to accomplish.

    Thanks

    Ed

    Wednesday, December 9, 2015 10:09 PM