After update %age complete of tasks and submitted tasks. Tasks are not coming to Project Owner PWA Approval Section. RRS feed

  • Question

  • I am the 'Project Owner' of the Project and saved and publish the Project .

    Some tasks are set to the 'Assignment Owner' because the tasks Resource is not available for few days.

    I saved and publish the project and those tasks which have 'Assignment Owner' are going to 'Assignment Owner' PWA (Tasks).

    But when 'Assignment Owner' update the '%age Complete' of the tasks and submit the tasks. Tasks are not coming to Approval center of my PWA.

    Although I have a permission of 'Approval timesheet' and 'Adjust Timesheet'.

    Tuesday, July 3, 2012 8:08 AM

Answers

All replies

  • Hi there,

    Who is the status manager for those tasks?

    THanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com

    Tuesday, July 3, 2012 8:25 AM
    Moderator
  • It is resolved

    Thanks

    but when i am going to change the status manager into project owner.

    in the list of status manager there is no name of project owner.

    how can i enter or change the status manager which is not in the list of status manager.

    Tuesday, July 3, 2012 8:32 AM
  • Hi John.Eddie,

    Open the project with the Project Owner account, the account should then appear in the list.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com

    • Marked as answer by John.Eddie Tuesday, July 3, 2012 8:44 AM
    Tuesday, July 3, 2012 8:39 AM
    Moderator
  • Before couple of minutes the 'Assignment Owners' can update the %age complete field in the PWA --> Tasks .

    But after 10 minutes the 'Assignment owner' try to update '%age complete' In Tasks page is not allow to do. and show in grey colour.

    whether it is in 'Awating Approval' .

    Tuesday, July 3, 2012 9:52 AM