Filter local resources in Project Pro 2013 RRS feed

  • Question

  • Hi,

    In Project Pro 2013 connected on a server:

    Is there a way to build a filter which selects in a project all the tasks assigned to Local Resources?

    Thanks

    Sunday, October 13, 2013 11:50 AM

Answers

  • This is beyond the capability of the out-of-the-box Custom Filter feature in Project Professional.  However, there is a way to accomplish this.

    A VBA macro could be written to flag the tasks that have a Local Resource assigned.  The macro would make use of a resource field named "Enterprise" which has values of either "Enterprise" or "Local".

    You could initiate the macro manually--or have it run when a project schedule opens.


    Dr. Edward M. Hanna, PMP President Data Express, Inc. Irvine, CA emhanna@sbcglobal.net


    • Edited by Edward Hanna Sunday, October 13, 2013 1:53 PM Remove signature
    • Marked as answer by Robert6156 Sunday, October 13, 2013 3:33 PM
    Sunday, October 13, 2013 1:53 PM