BCWP calculation error MSP 2007 RRS feed

  • Question

  • Is there a known bug in MSP 2007 BCWP calculation?  I have the Calculation Option for Earned Value set to [Physical % Complete].  BCWP appears to be calculating correctly (=[Physcial % Complete]*[Baseline Cost]) at the  resource level, yet the BCWP at the task level is incorrect and not equal to the roll-up (sum) of resources.  This is only true for in-process tasks, but not for every in-process task.