    We currently use top-level project bookings only with Enterprise Resources, and not at task-level placing resources against any part of the schedule.

    Is there any way of displaying any/total hours booked so far to a project actually within the schedule? i.e via a standard field or a custom field?

    We export time booked to top-level to an out of the box project server pivot-table spreadsheet, and the field used for time booked is 'Billable Actual Work'.  What feeds into this, or what reverse engineering is required to display this in MS Project?