  • Question

  • I have a client with several Sharepoint task lists, each tied to their own Project. I am trying to find a way to pull them all together for an easily-generated Executive view in a single Project file as subprojects, but to have them all sync with Sharepoint upon opening. Is this possible and if so, how?

    Thanks!!

    Thursday, March 24, 2016 7:28 PM

All replies

  • Jab570,

    Unfortunately, this is not possible. The master project will sync to the sharepoint site, but only as a project. None of the sub project will get synced as part of the master project.

    Alternatively you could build an executive view with the SharePoint Task Lists, using a Content Search Webpart or Content Editor web part.


    Cheers,

    Prasanna Adavi, Project MVP