none
I cant change %work complete in task page RRS feed

  • Question

  • I use project server 2010

    I was working with timesheet and task settings today. I dont know what did I do that now I cant change some of the task's % work complete in task page any more.

    I didn't have this problem,and I didnt use timesheet till today.

    Wednesday, September 21, 2011 1:36 PM

Answers

All replies

  • in the task settings and display area of the admin page, check to see what the default tracking method is and also see whether the check box forcing people to use the default method is selected.  If you checked the box for enforcement,  open / republish the schedule.
    Wednesday, September 21, 2011 1:42 PM
  • Hi Samira,

    Enable single entry mode under timesheet settings in server settings. Let us know if that works

    Thanks

    Ravishankar


    Ravishankar
    Thursday, September 22, 2011 4:58 AM