Percent Work Complete field in Timesheet RRS feed

  • Question

  • Is there a server setting required for users to be able to edit Percent work Complete in their Timesheet?   We are in single entry mode.
    Monday, September 24, 2012 2:27 PM

Answers

  • There are 3 default tracking methods

    1. % complete

    2. Actual work done and work remaining

    3. Actual work per period.

    Selecting SEM selects 3. for you above.  Therefore MS chose to disable the ability to enter any % complete.  I agree, it doesn't necessarily need to be read only, but that was the decision taken.


    Ben Howard [MVP] blog | web

    • Marked as answer by BayouB Tuesday, September 25, 2012 1:02 PM
    Tuesday, September 25, 2012 8:18 AM
    Moderator
  • BayouB --
     
    No, this is not possible because of your use of Single Entry Mode.  Using SEM, every team member must enter progress on a daily basis in the Timesheet page of PWA.  If team members NEED to be able to enter progress in the % Work Complete field, then your organization should NOT be using Single Entry Mode, and this setting should be disabled.  This will then allow the Project Server administrator to change the default method of tracking progress to % Work Complete.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Proposed as answer by PWMatherMVP, Moderator Monday, September 24, 2012 7:05 PM
    • Marked as answer by BayouB Tuesday, September 25, 2012 1:03 PM
    Monday, September 24, 2012 6:13 PM