Hi,
I face this issue couple of times, though i have correctly had calendar set to work 8 hours a day.
When i create plan , say first task has 2 days working from 16-May-2017 to 17-May-2017. Now when i assign a resource
start and finish change to 16-May-2017 to 18-May-2017. When i go to resource usage view it distributes work in following way
16 - 7 hours, 17 - 8 hours, 18 - 1 hour. I can go and change in the view the work field to make it 8, but my question is where am i going wrong.
Thanks
pm