Migration from Distribution Point within an SCCM2012 SP1 environment RRS feed

  • Question

  • Hi all,

    in an exisiting SCCM2012 SP1 CU2 environment (one CAS, four Primary sites and some DPs) we have the following problem: The schedule HW for the DPs are not available and we are planing to use another HW Model for a timeframe the correct model is available.

    When the new HW model is available I'm not sure how to move or migrate the content from the exisiting DP. Do you have this already done or ideas to do this.

    Thanks for your feedback.

    regards

    Wednesday, January 15, 2014 8:37 AM

Answers

  • Many possible ways to achieve that ... one would be: set up a temporary DP (using a temporary name). Set up the new DP once it arrived and configure it as a PullDP (so it will pull content from the temporary one). Wait until that process is finished. (Re-)configure the (new) PullDP so that it becomes a "classic" (non-Pull) DP. Remove the temporary one.

    Torsten Meringer | http://www.mssccmfaq.de

    • Marked as answer by carlicht Thursday, January 16, 2014 1:33 PM
    Wednesday, January 15, 2014 8:32 PM

All replies

  • Many possible ways to achieve that ... one would be: set up a temporary DP (using a temporary name). Set up the new DP once it arrived and configure it as a PullDP (so it will pull content from the temporary one). Wait until that process is finished. (Re-)configure the (new) PullDP so that it becomes a "classic" (non-Pull) DP. Remove the temporary one.

    Torsten Meringer | http://www.mssccmfaq.de

    • Marked as answer by carlicht Thursday, January 16, 2014 1:33 PM
    Wednesday, January 15, 2014 8:32 PM
  • Hi Torsten,

    thanks for your reply. I think the scenario you talk is the way for me to do this.

    Thanks and regards

    Carsten

    Thursday, January 16, 2014 1:32 PM