Require line approval before timesheet approval RRS feed

  • Question

  • We have enabled this feature month ago now I am seeing resources have not charged hours against a task but still showing as awaiting approval on status and when acted as a delegate I don't see any hours waiting to get approved in approval center. Timesheet status is showing as Pending submit what  is pending submit?

    It might be a possibility that people have charged hours by mistake and then reenter to another task.

    what should we do to see those timesheets in Resource manager approval center?

     
    Monday, March 30, 2015 4:14 PM

All replies

  • Project Help,

    As I answered in the other thread, please check the status managers of the tasks that are awaiting approval. 


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Monday, March 30, 2015 9:09 PM
    Moderator