  • Hi,

      I am developing a report for validation of resource time sheet, I want to include Administration tasks with dates as well. Any references or tips would be appreciated


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Monday, March 9, 2015 10:18 AM

Answers

  • Hi Syed,

    If you are willing to use the OLAP Cubes, you'll find 3 cubes dedicated to timesheet including administrative lines.

    Otherwise the [dbo.MSP_TimesheetLine_UserView] contains all timesheet information including non project work.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, March 9, 2015 10:33 AM
    Moderator

All replies

  • Hi Syed,

    If you are willing to use the OLAP Cubes, you'll find 3 cubes dedicated to timesheet including administrative lines.

    Otherwise the [dbo.MSP_TimesheetLine_UserView] contains all timesheet information including non project work.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, March 9, 2015 10:33 AM
    Moderator
  • Hi Guillaume,

     

      Thanks for your feedback. Appreciate your help


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Monday, March 9, 2015 10:53 AM
  • You're welcome!


    Hope this helps,