Allocating Resourses RRS feed

  • Question

  • Allocating Resources in PWA  does not show any alert for overallocation. But when we allocate the resources in Project Professional, it shows. Should we do the task of resource allocation in Project Professional only?
    Wednesday, November 7, 2012 11:31 AM

Answers

  • Hi,

    Yes you should do resource allocation in Project Professional. This for the reason you already stated that you do not see any information about a overallocation occuring within your project.

    With Kind Regards,

    Robin Kruithof


    Technical Consultant EPM

    • Marked as answer by Rishabh.J Wednesday, November 7, 2012 11:51 AM
    Wednesday, November 7, 2012 11:35 AM

All replies

  • Hi,

    Yes you should do resource allocation in Project Professional. This for the reason you already stated that you do not see any information about a overallocation occuring within your project.

    With Kind Regards,

    Robin Kruithof


    Technical Consultant EPM

    • Marked as answer by Rishabh.J Wednesday, November 7, 2012 11:51 AM
    Wednesday, November 7, 2012 11:35 AM
  • Thanks Robin