Master Project File - Creation of timeline. RRS feed

  • Question

  • Hi

    I have created a master project file with several projects inserted using the 'Insert Subproject' function. My issue is arising when I try to create a project timeline in the Master File. For example when I try to insert task 3 of Subproject 2, task 3 of Subproject 1 is inserted into the timeline. This seems to be caused by the repetition of task ID's within each inserted subproject.

    Appreciate any help you can provide.

    Dan

    Tuesday, December 23, 2014 3:49 PM

Answers

All replies

  • Hi D_Conn,

    Instead of adding the tasks that way, I would right click on the task in the Gantt chart and select Add Task to Timeline from the dropdown menu.


    Ben Howard [MVP] | web | blog | book | P2O

    Tuesday, December 23, 2014 3:56 PM
    Moderator
  • Thanks Ben

    Seem to have solved the issue. The master and all sub project files were saved in a folder on our teams Sharepoint. That folder location was moved after the master was created. Deleting and re-inserting the subproject files seems to have solved the issue.

    Thanks

    Dan

    Tuesday, December 23, 2014 5:42 PM