How to view completed tasks history in Projec server 2010 RRS feed

  • Question

  • Dear all,

    How can I view my completed tasks that approved by my manager?

    When  the task completion is 100% and approved, it disappear, and I don't know how to review it.

    Please help. Thanks very much.

    Saturday, June 2, 2012 2:22 AM

Answers

  • DoLeVu --
     
    The only way you can see tasks approved by your project manager is if he/she is NOT using the Close Tasks to Update feature, which you have already asked questions about.  When your project manager used the Close Tasks to Update feature, that feature REMOVES the tasks from your Tasks page so that you CANNOT enter any additional task progress on those tasks.  It is a formal defined method for preventing team members from adding additional work to a task that the team member said he/she has already completed.
     
    So, if your project manager is using the Close Tasks to Update feature, you CANNOT see your completed tasks any more, so there is no way to see the history.  Given your questions about this feature, I suspect your project manager is not using the feature correctly.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by DoLeVu Sunday, June 3, 2012 8:23 AM
    Sunday, June 3, 2012 1:29 AM
    Moderator

All replies

  • DoLeVu --
     
    The only way you can see tasks approved by your project manager is if he/she is NOT using the Close Tasks to Update feature, which you have already asked questions about.  When your project manager used the Close Tasks to Update feature, that feature REMOVES the tasks from your Tasks page so that you CANNOT enter any additional task progress on those tasks.  It is a formal defined method for preventing team members from adding additional work to a task that the team member said he/she has already completed.
     
    So, if your project manager is using the Close Tasks to Update feature, you CANNOT see your completed tasks any more, so there is no way to see the history.  Given your questions about this feature, I suspect your project manager is not using the feature correctly.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by DoLeVu Sunday, June 3, 2012 8:23 AM
    Sunday, June 3, 2012 1:29 AM
    Moderator
  • Thanks very much, Dale.
    • Edited by DoLeVu Sunday, June 3, 2012 8:23 AM
    Sunday, June 3, 2012 7:46 AM
  • DeLeVu --
     
    You are more than welcome for the help, my friend!  :)

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Sunday, June 3, 2012 9:41 PM
    Moderator