  • If you calculate the EV (BCWP) in my plan uses the field Psyhical % Complete.MS Project 2010 not able to correctly calculate the for other than the original Baselines. When you set the Advanced options Baseline for EV calculation: Baseline1 or Baseline2 field EV (BCWP) value field is invalid. What is interesting is still applied to the primary Baseline. The odd thing, however, is that the EV (BCWP) in the same plan only appears in the Task Usage view is correct and applies to the specified baseline in Advanced options for example Baseline3, why?

    Txn Darek<o:p></o:p>


    Thursday, May 9, 2013 9:36 AM

All replies

  • I cannot reproduce this problem.  What do you mean by "value field is invalid"?

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.