Project Server 2007 : Unapproved Timesheet RRS feed

  • Question

  • Is it possible to build a Data Analysis view (OLAP Cube) which displays all the Unapproved Timesheet in the company?

    Thanks

    Wednesday, January 5, 2011 9:46 AM

Answers

  • Hi,

    if you are looking also for timesheets not even created, the answer is no - unfortunately. Timesheet records are created after creation of timesheets in RDB.

    If you only need a list of timesheets at least created but not yet approved, it is possible. Use cube Timesheet. Add Timesheet Status as filter and deselct approved. Use resource list to rows and timesheet period to row or columns - depend how you want to see. Add a measure to this view, like ACtual Work Billable. This should give you an overview. Or I did I miss something in your question?

    Regards
    Barbara

    • Marked as answer by WLID1966 Wednesday, January 5, 2011 10:31 AM
    Wednesday, January 5, 2011 10:00 AM