Time charged in timesheet but not showing up in project RRS feed

  • Question

  • Hi,

    Resource charged time in timesheet , approved by PM and functional manager the time shows in timesheet but not in project for those days?

    I have recalled the timesheet,resubmitted and publish project again still don't show up 

    Anyone knows why

    Friday, March 20, 2015 3:20 PM

All replies

  • Under Tasks, history check if there are items in Pending Status.

    Sometimes some errors prevent the Project Server to write on the Project Plan (if the Project Plan is checked-out) or if the Project has some required Custom Fields on it without value.

    Cheers

    Monday, March 23, 2015 2:57 PM
  • Just to confirm, double check whether the project is published

    Open PWA --> Approvals --> History --> Status updates

           -Ensure the Approval date, action and published status, publish the plan if it is unpublished.

    If that doesn't help,

    -->Recall the timesheet, Remove that problematic task which was submitted earlier (note down the hours)

    --> Add the assignment again -->Submit the hours, approve and check it again.

    Note : there are two possible reasons, either the project plan is not published after the approval or the assignment id not mapped with the appropriate project plan.


    Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management

    Monday, March 23, 2015 7:56 PM
    Moderator