Budget Cost Resource gets deleted RRS feed

  • Question

  • Hi,

    Our client is using Budget Cost resources extensively and for some of the projects they have complained that Budget Cost Data (Including Baseline budget cost) is deleted automatically.

    Unfortunately, they couldn't reproduce the steps, and this has happened 4 times on different projects in last 2 months. Only thing common in all 4 cases is that Projects were re-baselined at some stage. 

    Are you aware of any scenario where Project Server would delete Budget cost data from Project schedule ? 

    Monday, July 1, 2013 6:00 AM

All replies

  • The above doesn't provide info on project server version and complete scenario.

    I know of a similar instance fixed in June 2012.

    Description of the Project Server 2010 hotfix package (Pjsrvwfe-x-none): June 26, 2012

    'http://support.microsoft.com/kb/2598375'

    When you change a project summary task in Project Server 2010, the timephased budget cost information for cost resources is lost.

    Monday, July 1, 2013 6:44 PM