Resource Capacity job ran successfully, but Capacity is not available in Resource Availability View/RDB RRS feed

  • Question

  • Hi,

    in our Project Server 2010 installation we found out that the resource capacity for all resources is 0 in all views as well as in the reporting database. We've checked the Advanced Server Settings:

    Active capacity view:
    Months behind: 2
    Months ahead: 10

    Calculate resource full-time equivalent from:
    resource base calendars

    Also in the Central Administration/Monitoring the job 'Project Server Service Application:PWA' Resource Capacity job was logged as successfully executed.

    What can I do to find the cause?

    Thanks,

    Peter



    Tuesday, December 18, 2012 6:31 PM

Answers

All replies

  • Hi there,

    Do you have the Team Assignment Pool check box checked for some / all of the resources?

    Thanks

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Tuesday, December 18, 2012 6:45 PM
  • Peter --
     
    Do you have the Max. Units value set to 0% for every resource in your Enterprise Resource Pool, by chance?  Let us know and we will try to help.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, December 18, 2012 9:27 PM
  • Hi Dale and Paul,

    no, resources are not a team assignment pool nor the capacity is set to 0%. Any thought how to figure out what internally is done and how to analyze this?

    Thanks,

    Peter

    Tuesday, December 18, 2012 9:31 PM
  • Hi,

    after reviewing it it turned out that some resources were team assignment pools.

    Thanks,

    Peter

    Friday, December 21, 2012 11:41 PM