none
How task progress update when add difference line category RRS feed

  • Question

  • In some period , I have Task A line category is standard 

    and I choose "select from existing assignments" menu for add this task 

    with difference line category(Travelling).


    I fill hour in Task A line category "Travelling", and summit to report progress. 

    In Process status column show 'Awaiting approval' both Task A line (Standard and Travelling). 


    After PM approve Task A, Process status in Task A category 'Travelling' still show 'Awaiting approval'

    I confuse about it. Cloud anybody have any ideas?



    Thank you, :)


    Monday, June 10, 2013 10:39 AM

All replies