MS Project 2010 Task 0 RRS feed

Answers

  • AKH162,

    It's not something the user can create. It is created automatically by Project and is called the Project Summary Task. Go to Format/ShowHide group and check the option to display the Project Summary Task.

    John

    • Marked as answer by AKH162 Monday, March 18, 2013 3:12 PM
    Monday, March 18, 2013 2:54 PM

All replies

  • AKH162,

    It's not something the user can create. It is created automatically by Project and is called the Project Summary Task. Go to Format/ShowHide group and check the option to display the Project Summary Task.

    John

    • Marked as answer by AKH162 Monday, March 18, 2013 3:12 PM
    Monday, March 18, 2013 2:54 PM
  • Perfect answer.  Thanks for much.
    Monday, March 18, 2013 3:13 PM
  • AKH162,

    You're welcome and thanks for the feedback.

    John