Auto Scheduling Issue RRS feed

  • Question

  • I am using Project Online. My current setting in Project --> Options --> Schedule is as shown below. 

    Consequently I have to remember to hit F9 to recalculate the schedule. It was never the case previously. Seems bizarre, I am not sure how this happened. 

    Should default setting for auto scheduled projects be:
    Calculate project after each edit = On
    Thanks for the feedback. 

    Wednesday, April 15, 2015 6:59 AM

All replies

  • Indeed the default seetting should be ON. I suggest that you reset the value to ON. It should not change by itself.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, April 15, 2015 8:47 AM
    Moderator