Missing {Project_Name} in Resource Notification emails RRS feed

  • Question

  • When our resource managers receive notifications for schedule changes on a project, the project name is not populating: 

    Hello! Here are the latest schedule changes to your project {Project_Name}.{LineBreak}
    You own the following tasks:   
    Assigned to: Technology Transfer Team   
    Task Name: Develop Maintenance Manuals   
    Start: Friday, July 13, 2018  Finish: Monday, July 16, 2018  Work: 16h  Remaining
    Work: 16h  Percent Complete: 0

    The project name is showing in the subject line and the intro text on the notification email, but not the inset of the task details.  Anyone have an idea of whether this is a bug in PWA or something an admin can fix?

    Thanks!

    Friday, March 9, 2018 3:06 PM

All replies

  • As I understand it there is no option to edit the content of the email that is generated by PWA to provide more granular context. The format of the email is something that is buried deep within the workings of PWA and is not something that is made available to users to edit or modify - perhaps you should vote on this as an enhancement request - sorry!

    With good wishes,

    Dominic

    Microsoft Project Evangelist

    Twitter:   LinkedIn:    Web:   