  • There have been numerous discussions on this topic, but no answer. The issue is the following message:

    "The task list was last synchronized to a different project plan. If you continue the task list will be appended to the project plan."

    Steps are as follows:

    1) Create a MS Project Plan

    2) Create a Sharepoint Project Task list

    3) Sync and Save the file to the Sharepoint site

    4) Check-out and open the MS Project plan.

    5) Make changes to Plan

    5) Sync file to Sharepoint Project Task List

    6) Save file

    7) Check-in file

    Everything works fine up to this point. Now change one factor (which does occur) step 6 as follows:

    1) Create a MS Project Plan

    2) Create a Sharepoint Project Task list

    3) Sync and Save the file to the Sharepoint site ( I chose this option to manage versions)

    4) Check-out and open the MS Project plan.

    5) Make changes to Plan (add 500+ tasks) Save/sync file every chance I get (auto-save set for 5 minutes)

    6) SYSTEM or MS Project crashes before saving changes

    7) Reopen MS Project Plan and try to Sync: Error:

    "The task list was last synchronized to a different project plan. If you continue the task list will be appended to the project plan."

    Is there a solution to this problem?

    Tuesday, February 12, 2013 9:22 PM

All replies

  • Did you happen to do a COPY/PASTE when you added the 500 tasks.   If you did, that's your problem.

    As a general rule try avoiding COPY/PASTE, especially of rows, because you are copying over 500 other fields and they often have unique IDS that can cause issues.

    Cheers


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Friday, April 5, 2013 1:33 PM
    Moderator