How to increase task duration in Timesheet (PWA 2010) RRS feed

  • Question

  • Hi,

    We are not using Single Entry Mode. A team member is entering time in his/her timesheet. At the end of his/her assignment he needs to enter time on 2 days after the scheduled finish date. If the 2 days are on the same week, it's easy. But if the 2 days are on the next week, the task doesn't appear any more.

    What would be the best solution?

    Thanks

    Sunday, October 14, 2012 9:26 AM

Answers

  • Hi,

    unfortunately, without SEM, user is not able to change Remaining Work or Finish Date in Timesheet. An easy way to prepare next week's timesheet.

    But in timesheet of next week, he can use Insert Row - Insert task. Select appropriate project and missing task to report some more time on it.

    Not sure if this is an option?
    Regards
    Barbara

    • Marked as answer by WLID1966 Sunday, October 14, 2012 1:13 PM