Changing a reports axis RRS feed

  • Question

  • I am attempting to change the resource over allocation report axis from individual dates to months.

    Also trying to extend those months further to match the project

    Any help would be very appreciated!!

    Friday, September 25, 2015 3:27 PM

All replies

  • Hi,

    Are you talking about the resource overallocation report from the report tab in MS Project 2013?

    In case you are, you can simply change the timescale of the right diagram which has the resourcesz as series and time as axis ("edit" button near "time category). You can also choose the start and finish date.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Friday, September 25, 2015 3:33 PM