  • Does the setting of a project's Status Date affect the publishing of it's custom enterprise fields?

    I think not but someone in my org someone said the reason that a set of custom enterprise project level cost fields that did not populate our PWA > Project Center custom view is because the project's status date was not set (ie., 'NA') when it was published.  I think not, but just wanted to check here.

    We are using Project Pro 2013 and Project Online.

    Thanks in advance,


    \Spiro Theopoulos, Montreal, QC (Canada)

    Thursday, June 11, 2015 1:09 AM

Answers

  • Hi Spiro,

    No, Project Status date does not affect custom enterprise field unless you are using the custom enterprise field as a calculated field and referring the [status date] field in the formula.