Progress Bar (Complete Through) does not display correctly when Marking on track RRS feed

  • Question

  • In some instances, clicking "Mark On Track" indicates "progress" past the current status date. I have removed performance, resources duration and then reset them all (Which, by the way fixes my split tasks). It still does not work in all cases for displaying progress past the status date. This is in a file that I was given that started in 2003, was then run in 2007 and is now being run in MS Proj 2010.
    • Edited by Ray_Flowers Wednesday, March 12, 2014 8:48 PM
    Wednesday, March 12, 2014 8:47 PM

Answers

  • Hi Ray,

    Since this issue is only occuring on a file that has "travelled" a lot (and too much) between different Project versions (that often triggers issues), I'd suggest to try to repair it, using the "save for sharing" functionality or save it as XML.

    See "how-to-do" articles below:

    • http://project.mvps.org/faqs.htm#Handling_project_file_corruption_and/or_bloat
    • http://epmablog.com/microsoft-project-2010save-for-sharing-feature/

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Ray_Flowers Wednesday, April 16, 2014 6:24 PM
    Wednesday, March 12, 2014 9:23 PM