How to change the Timescale in a "project" Gantt view (PWA 2007) RRS feed

  • Question

  • Hi,

    How to change the Timescale in a "project" Gantt view (PWA 2007) ?

    Instead of weeks and days, I want Month and Weeks.

    Thanks

    Thursday, March 1, 2012 9:23 AM

Answers

  • Hi,

    in Actions menu, you have "Tool Bar". Just enable and it will be displayed.

    Regards
    Barbara

    • Marked as answer by WLID1966 Thursday, March 1, 2012 11:23 AM
    Thursday, March 1, 2012 10:41 AM
    Moderator
  • Yes, it will. In 2007, you are only switching views, not PDPs.

    Barbara

    • Marked as answer by WLID1966 Thursday, March 1, 2012 12:40 PM
    Thursday, March 1, 2012 12:32 PM
    Moderator

All replies

  • Hi,

    to use zoom buttons is not sufficient for you (loupe + and -)?

    Regards
    Barbara

    Thursday, March 1, 2012 9:38 AM
    Moderator
  • Hi Barbara,

    OK, I found the Zoom in and the Zoom out tools in the Actions menu, but they are not handy at this place!

    Is it possible to add them on the tool bar?

    Thursday, March 1, 2012 10:38 AM
  • Hi,

    in Actions menu, you have "Tool Bar". Just enable and it will be displayed.

    Regards
    Barbara

    • Marked as answer by WLID1966 Thursday, March 1, 2012 11:23 AM
    Thursday, March 1, 2012 10:41 AM
    Moderator
  • Wooh!

    It was well hidden!

    And now this tool bar will be displayed by default on every Project Details page?

    Thanks again

    Thursday, March 1, 2012 11:26 AM
  • Yes, it will. In 2007, you are only switching views, not PDPs.

    Barbara

    • Marked as answer by WLID1966 Thursday, March 1, 2012 12:40 PM
    Thursday, March 1, 2012 12:32 PM
    Moderator
  • In Sharepoint 2007, under Action for Gnatt View, I do not see "Tool Bar," "Zoom In," " Zoom Out." How do I get these?