Strange behavior of Leveling feature in French Project 2016 RRS feed

  • Question

  • Hi,

    In the English version of Project 2016 I create 3 tasks running in parallel and using the same resource. The leveling feature is able to set the 3 tasks one after the other. If the first task is completed at 100% and I run another leveling because there is another over-allocation in the project, my 3 tasks don't move. That's what I expect. OK.

    

    If I create a similar project In Project 2016 FR, the behavior is very strange: If Task 1 is finished and I have to run a new leveling because of an over-allocation somewhere else, Task 2 and Task 3 shift to the project start, somewhat like Task 1 did not exist:

    And if T2 is complete : task T3 shifts to the left again. So the resource did 3 tasks in parallel !

    Is it a known issue? any workaround?

    Thanks


    • Edited by WLID1966 Sunday, April 9, 2017 11:43 AM
    Sunday, April 9, 2017 11:38 AM

Answers

  • Hi,

    I noticed today that this issue has been corrected in French version

    Thanks

    • Marked as answer by WLID1966 Monday, June 5, 2017 5:36 PM
    Monday, June 5, 2017 5:36 PM

All replies

  • In the first case you have leveled first and then marked T1 finished.

    In the second case (I think) you have marked T1 finished and then leveled.

    Leveling won't move a task which is finished, because actuals trump everything else.

    Can you show us the result of the FR version with leveling first and then marking T1 finished?

    Sunday, April 9, 2017 10:38 PM
  • Hello Trevor

    01-Initial state :

    02-After the first leveling :

    03-Task 1 is complete :

    04-A new leveling has been run:


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    Monday, April 10, 2017 9:43 AM
  • Hi,

    I noticed today that this issue has been corrected in French version

    Thanks

    • Marked as answer by WLID1966 Monday, June 5, 2017 5:36 PM