Migration from MS Project 2003 to MS Project Server 2010 RRS feed

  • Question

  • Hi, I am looking to get a way to migrate from the existing shared workspace which contains the MS sub Projects (including the Master Project) to MS Project Server 2010. There are currently 20 sub projects with three levels of abstraction. The Level 1 is the Master Project. The Level 2 contains individual projects for each streams (requirements; design; build and deployment). The level 3 contains subprojects within each stream. The Master project cannot be shifted alone as this will break the linkage between the sub-project and the Master Project. My question is there any way to shift the whole workspace containing all the sub-projects(and the Master Project) to the MS Project Server 2010 environment without breaking the existing links.

    Many thanks!